Dominion, Duke cancel Atlantic Coast Pipeline

Published 3:17 pm Sunday, July 5, 2020

Getting your Trinity Audio player ready...

Dominion Energy and Duke Energy on Sunday announced the cancellation of the Atlantic Coast Pipeline due to ongoing delays and increasing cost uncertainty which threaten the economic viability of the project.

Despite last month’s 7-2 U.S. Supreme Court decision, which vindicated the project and decisions made by permitting agencies, recent developments have created an unacceptable layer of uncertainty and anticipated delays for ACP, the companies announced in a press release Sunday.

The litigation risk, among other continuing execution risks, make the project too uncertain to justify investing more shareholder capital, the companies said.

Email newsletter signup

A series of legal challenges to the project’s federal and state permits has caused significant project cost increases and timing delays. These lawsuits and decisions have sought to dramatically rewrite decades of permitting and legal precedent including as implemented by presidential administrations of both political parties. As a result, recent public guidance of project cost has increased to $8 billion from the original estimate of $4.5 to $5 billion. In addition, the most recent public estimate of commercial in-service in early 2022 represents a nearly three-and- a-half-year delay with uncertainty remaining.

Thomas F. Farrell, II, Dominion Energy chairman, president, and chief executive officer, and Lynn J. Good, Duke Energy chair, president, and chief executive officer, said:

“We regret that we will be unable to complete the Atlantic Coast Pipeline. For almost six years we have worked diligently and invested billions of dollars to complete the project and deliver the much-needed infrastructure to our customers and communities.

“Throughout we have engaged extensively with and incorporated feedback from local communities, labor and industrial leaders, government and permitting agencies, environmental interests and social justice organizations. We express sincere appreciation for the tireless efforts and important contributions made by all who were involved in this essential project. This announcement reflects the increasing legal uncertainty that overhangs large-scale energy and industrial infrastructure development in the United States. Until these issues are resolved, the ability to satisfy the country’s energy needs will be significantly challenged.”

The Atlantic Coast Pipeline was initially announced in 2014 in response to a lack of energy supply and delivery diversification for millions of families, businesses, schools and national defense installations across North Carolina and Virginia.

The companies remain steadfast in the belief that fuel diversity, including renewables, nuclear, and natural gas, is critical for reliably and sustainably serving customers and communities, according to the press release. Both will continue aggressively pursuing the development of renewables, storage, nuclear license renewals, electric vehicle infrastructure, energy delivery infrastructure, as well as energy efficiency and demand side management programs to meet their customers’ needs while creating jobs and spurring new business growth in the aforementioned regions.

Dominion Energy and Duke Energy will separately provide additional information for their respective stakeholders and shareholders as relates to the company-specific financial, environmental, operational, and other impacts of this announcement.